CLL completed the foundation works at Madeira Lane for a new NEO apartment building that offers 99 new free hold apartments in the centre of Grafton.
This project encompassed the construction of 129 retaining and building piles and crane base piles between permanently cased piles and standard RC piles starting on mid-June and extending until beginning of Sep, The project was completed within time and budget, great effort from the crew on site that worked hard supporting our client as well as guiding the earthwork subcontractor through tricky staging and excavation sequence. The removal of the equipment off site was worth a watch and we managed to learn some good lessons if in the future we need to lift our EK110 with a mobile Crane