CLL were engaged by LT McGuiness to Install over 200No, 9m Long Soil Nails. The initial methodology was to construct these nails using a rope access crew.
However, CLL were able to work in with the client and find a gap in the building construction programme to utilise CLL’s Teleboom Rig from within the building footprint, therefore, reducing the duration and cost of soil nail installation without impacting the main building programme.